- DAQ receives written notice that facility is not subject to MACT YYYY or ZZZZ - 05/30/06.
- T07 issued for renewal of Phase II acid rain portion of pmt - 12/14/04. (E.Martin)
- Testing for units 3 & 6 after repairs show compl. with NOx limits - 09/16/05. (J.Hammond)
- Applic. is withdrawn. Unit will be installed at Lee Plant - 06/21/05. (E.Martin)
- DAQ conducts inspection - 02/18/05. (S.McKinney)
- DAQ receives applic. for new simple-cycle combustion turbine - 12/14/04. (E.Martin)
- DAQ conducts inspection of Richmond County Comb. Turbine - 05/25/04. (S.McKinney)