Notes from Discussion with BK

(June 8, 2006)

Hornwood Modification to add control device: The applicant is sending the updated engineering review for the control device.

Trans Carolina Products greenfield application: Karen Massena has worked closely with DAQ on this application. This is a priority application for BK and will be issued before SV goes on vacation on June 27th.

BK has two pending regional reviews for Title V. He expects Goodyear permit for the temporary boiler to be issued within the next few days. It will include a MACT avoidance condition that specifies the 180-day limit before the boiler become subject to MACT.
The Jordan Lumber permit will be revised by WW to correct the MACT Subpart DDDDD language.